Update 2/27 – 3/3

Installation of power vaults and the joint utility trench will continue through this week.

 

 

Advertisements

Update 2/20 – 2/24

Seton Construction will continue with installing water and storm utilities. They will also be installing power vaults and doing the joint utility trench at Howard Street and Park Street.