Update 1/2 – 1/6

No construction will be done onsite Monday, January 2nd due to the holiday. Seton Construction will be back onsite Tuesday, January 3rd and will be starting on the Joint Utility Trench which holds the conduit for the power, phone and cable lines.

 

 

 

Advertisements

Update 12/19 – 12/23

Seton Construction will start working on the connections of the water main to both 7th Street and 9th Street starting Wednesday, December 21st. The water will be shutdown for the connection on Thursday, December 22nd starting at 7:30am.

Please note that if the water shutoff affects your home you will be notified by the City of Port Townsend Water Department early in the week.

While that works is being done Discovery Rd. will go down to one lane of traffic that will be controlled by flaggers.

Update 12/5 – 12/9

Seton Construction will continue installation of the 10″ water main on Howard St. They will also start installation of the 8″ water main located on 7th Street.

NOTICE: Water will be shutoff on Howard St. between 10th Street and Discovery Rd. on Tuesday, December 6th between the hours of 9:00am and 3:00pm. All homeowners have been notified by the City of Port Townsend Water Department.