Update 11/21 – 11/30

Installation of the sewer main and side sewers on 7th Street will get underway. Seton will also be starting the 10″ water main at 10th Street and Howard Street.

There will be no construction on Thursday, November 24th and Friday, November 25th due to the Thanksgiving Holiday. Construction will resume on Monday, November 28th.

Advertisements

Update 11/7 – 11/11

Seton Construction will continue to work on the sewer main along with the side sewers and some sewer pipe testing. Testing will also be done on the storm main that has been installed. The construction site will be receiving deliveries of materials for working on the water main that should start the following week.